HENDON PHASE 5 – PROGRESS

Concrete crushing begins after service termination delays, asbestos removal and soft strip have all been completed. Pushing on full steam ahead with 10 excavators on site to meet programme requirements for our 5th phase for a valid client at the West Hendon Estate.